How to lay a concrete shed base (UK guide)
A concrete base is the most solid foundation you can give a shed: flat, dry and long-lasting. It’s a satisfying weekend job if you plan the materials and the pour properly.
The short version
Mark out a base the size of your shed’s footprint (or slightly larger), dig out about 175–200 mm, compact 75–100 mm of MOT Type 1, set timber formwork, and pour 100 mm of concrete. For a 3 × 2.4 m shed that’s about 0.72 m³ of concrete, roughly 11 bags of cement with 1.6 tonnes of ballast if you mix your own.

How big should the base be?
Most shed makers recommend a base that matches the shed’s footprint, or one that’s slightly larger so you have a little working room. Check your shed’s instructions: some prefer the walls to sit just inside the edge so rain runs off rather than onto the base. Measure the floor frame, not the roof, which overhangs.
The layers
| Layer | Depth | Notes |
|---|---|---|
| MOT Type 1 sub-base | 75–100 mm, compacted | Firm, level support. Go deeper on soft ground. |
| Damp-proof membrane (optional) | — | Polythene under the concrete helps keep the base dry |
| Reinforcement mesh (optional) | Set within the slab | A142 helps control cracking, especially on softer ground |
| Concrete | About 100 mm | Thick enough for a typical garden shed |
Preparing the ground

- Mark the area with pegs and string, and check it’s square by measuring both diagonals: they should be equal.
- Dig out turf and soil to about 175–200 mm.
- Spread MOT Type 1 in layers and compact each with a plate compactor.
- Build timber formwork around the edge with the top set at the finished concrete height, and check it’s level.
Mixing and pouring

For a base this size you can mix your own, use bags, or order ready-mix. If mixing, a common recipe is 1 part cement to 5 parts all-in ballast. Mix in a cement mixer, adding water gradually until the concrete is workable but not runny.
- If using mesh, set it on spacers so it sits within the slab, not on the ground.
- Fill the formwork, working the concrete into the corners with a shovel.
- Level it by drawing a straight timber board across the formwork in a sawing motion (tamping).
- Finish the surface with a float for a smoother top.
Worked example: a 3 × 2.4 m base
| Item | Amount | Calculator |
|---|---|---|
| Concrete (100 mm) | 0.72 m³ | Concrete |
| Or mix your own at 1:5 | About 11 × 25 kg bags of cement and 1.6 t of ballast | Ballast and cement |
| MOT Type 1 (100 mm) | About 1.5 t: two 0.85 t bulk bags | MOT Type 1 |
| A142 mesh (optional) | 1 standard 4.8 × 2.4 m sheet, cut to size | Concrete mesh |
Add about 10% to the concrete for uneven ground. If you’d rather not mix 0.72 m³ by hand, see our guide to bags, ready-mix or on-site mixed concrete.
Curing
Keep the concrete damp and covered for the first few days, and protect it from frost and heavy rain. Concrete gains most of its strength over the first week or so; wait at least several days before building the shed on it, and follow your shed maker’s guidance.
Mistakes to avoid
- A base that isn’t square: check the diagonals before pouring.
- Skipping the sub-base on soft or clay ground.
- Too wet a mix, which weakens the concrete.
- Pouring in frost, or with frost forecast.
- Running short: always add a margin.
Calculators for this job
More guides
Barrowload guide · UK · Figures are typical; always check your product and local rules.