How to lay a patio (UK guide)
A good patio is mostly about what’s underneath it. Slabs laid on a solid, compacted sub-base and a full bed of mortar stay flat for years; slabs laid on a few dabs of mortar over loose soil rock and crack within a winter or two.
The short version
Dig out about 16–17 cm. Lay 100 mm of compacted MOT Type 1, then bed each slab on a full layer of mortar about 40 mm deep, with a gentle fall away from the house. For a 4 × 3 m patio in 600 × 600 mm slabs, that’s about 34 slabs, three bulk bags of Type 1, and 8 bags of cement with 0.82 tonnes of sharp sand.

Before you start
Height. Keep the finished patio at least 150 mm below your damp-proof course, the line usually visible a couple of bricks above the ground.
Fall. Slope the patio away from the house so rain runs off. A fall of around 1 in 60 is commonly used: about 5 cm over 3 m.
Where the water goes. The run-off needs somewhere to soak away, such as a lawn, a border or a drain.
The layers, from the bottom up

| Layer | Depth | Notes |
|---|---|---|
| MOT Type 1 sub-base | 100 mm, compacted | The strength of the patio. Compact in layers. |
| Mortar bed | About 40 mm | Sharp sand and cement, about 4:1, laid as a full bed under each slab |
| Slabs | About 20–25 mm | Porcelain is thinner; natural stone varies |
| Joints | About 10 mm | Filled with mortar or a brush-in jointing compound |
Add those up and you need to dig out roughly 16–17 cm below the finished height, a little more for thick natural stone.
Worked example: a 4 × 3 m patio
| Item | Amount | Calculator |
|---|---|---|
| 600 × 600 mm slabs (10 mm joints, 5% extra) | 34 slabs | Paving slab |
| MOT Type 1 at 100 mm | About 2.5 tonnes: three 0.85 t bulk bags | MOT Type 1 |
| Mortar bed at 40 mm, 4:1 | 8 × 25 kg bags of cement and 0.82 t of sharp sand | Sand and cement |
| Soil dug out (12 m² × 17 cm) | About 2 m³, or 2.6 m³ once loose | Skip size |
Choosing your slabs
| Slab type | Good points | Watch out for |
|---|---|---|
| Porcelain | Hard-wearing, stain-resistant, consistent sizes | Needs a bonding primer; harder to cut |
| Natural sandstone | Warm, natural look; each slab is unique | Varies in thickness; may need sealing |
| Concrete | Budget-friendly, wide range of finishes | Colours can fade over time |
Tools you’ll need
A spade, wheelbarrow, rake, string lines and pegs, a long spirit level, a rubber mallet, a pointing trowel and a cement mixer. Hire a plate compactor for the sub-base, and an angle grinder with a suitable blade if you need to cut slabs (porcelain needs a dedicated porcelain blade). Wear gloves, eye protection and a dust mask when cutting.
Laying the slabs

- Set out string lines at the finished height, including the fall.
- Mix a small batch of mortar, damp and workable rather than wet. Only mix what you can lay in about an hour.
- Spread a full bed for one slab at a time, slightly thicker than needed.
- Lay the slab and tap it down with a rubber mallet until it’s level with the string line and the fall is right.
- Use spacers to keep the joints even, and check with a spirit level as you go.
- Leave it to set, keeping off it for a day or two, then fill the joints.
If you’re using porcelain, most manufacturers recommend painting the back of each slab with a bonding primer before laying, because porcelain absorbs so little water that ordinary mortar struggles to grip it.
Mistakes to avoid
- Spot bedding (five dabs of mortar): it leaves hollows that crack slabs and let water sit underneath.
- No fall, or a fall towards the house.
- Laying in frost, or when frost is forecast before the mortar sets.
- Building sand instead of sharp sand in the bed: it’s too soft.
- Skipping the sub-base on soft ground.
Calculators for this job
More guides
Barrowload guide · UK · Figures are typical; always check your product and local rules.