Barrowload

Home / Australia calculators / Building and hardscape

Concrete mix calculator

Work out how much cement, sand and aggregate you need for concrete. Australian units: metres, centimetres and tonnes. Results update as you type.

How much cement, sand and aggregate do I need?

Concrete materials = slab volume × 1.54 (dry materials shrink when mixed), split by the mix ratio. A 3 m × 3 m slab, 10 cm thick, at 1:2:3: Buy 17 × 20 kg bags of cement and 0.74 tonnes of sand and 1.11 tonnes of aggregate. Add about 10% for waste.

On this page
Mixing cement, sand and aggregate

Key facts

  • 1:2:3 (cement : sand : aggregate) is a common mix for slabs and paths.
  • Dry materials need about 1.54 times the finished volume.
  • 1 m³ of 1:2:3 concrete needs about 370 kg of cement (19 × 20 kg bags).
  • For larger slabs, premixed concrete is usually easier.

Common mix ratios

RatioTypical use
1:2:3Slabs, paths, driveways
1:2:4General purpose
1:3:6Footings and mass fill

Ratios are by volume, cement first. Follow any engineer’s specification for structural work.

Mixing tips

  • Mix dry materials first, then add water a little at a time.
  • Too much water weakens concrete; aim for a workable, not runny, mix.
  • Keep cement dry and use it before its use-by date.
  • Hire a mixer for anything more than a few barrow loads.

What mistakes should I avoid?

  • Forgetting the 1.54 dry-volume factor, and running short.
  • Adding too much water.
  • No extra for waste: add about 10%.
  • Old or damp cement, which won’t set properly.

How is it calculated?

Dry volume = slab volume × 1.54. Each material = dry volume × its share of the ratio. Cement is converted at 1,440 kg per m³ into bags; sand and aggregate at about 1.6 t/m³.

Worked examples

Garden slab: Buy 17 × 20 kg bags of cement and 0.74 tonnes of sand and 1.11 tonnes of aggregate. Add about 10% for waste.

Small shed base (2.4 × 2.4 m): Buy 11 × 20 kg bags of cement and 0.47 tonnes of sand and 0.71 tonnes of aggregate. Add about 10% for waste.

What figures do we use?

  • Dry-volume factor of 1.54
  • Cement at 1,440 kg per m³
  • Sand and aggregate at about 1.6 t/m³

These are typical figures; your materials and supplier may differ.

Common questions

How many bags of cement per cubic metre of concrete?

About 19 × 20 kg bags at 1:2:3.

Why multiply by 1.54?

Dry sand, aggregate and cement have air gaps that close up when mixed with water, so you need more dry material than the finished volume.

What is aggregate?

Crushed rock or gravel, often 10–20 mm, which gives concrete its strength.

Bags of premix or mix my own?

Premix bags are convenient for small jobs; mixing your own is usually cheaper for larger ones.

How much water do I add?

Add gradually until the mix is workable but not sloppy. Too much water weakens concrete.

Do I need to add extra?

Yes, about 10% for waste and uneven ground.