Home / Australia calculators / Building and hardscape
Skip bin size calculator
Work out what size skip bin you need for soil and rubble. Australian units: metres, centimetres and tonnes. Results update as you type.
What size skip bin do I need?
Dug-out volume = length × width × depth × bulking factor (soil takes up more space once dug). Digging out 5 m × 4 m of topsoil 15 cm deep: Book 1 × 4 m³ skip bin for about 4.5 tonnes of topsoil. Check the hire company’s rules for heavy waste.
On this page

Key facts
- Soil grows by roughly 12–30% in volume once dug; broken concrete by about 60%.
- Heavy waste such as soil and concrete often has bin size or weight limits.
- A cubic metre of soil can weigh 1.5 tonnes or more.
- Weight often limits a bin before space does.
Skip bin sizes
Skip bins are usually sold by the cubic metre, commonly from about 2 to 8 m³ for household jobs. Many companies have separate rules and prices for heavy waste such as soil, concrete and bricks, often with smaller maximum bin sizes or weight limits. Check before booking.
Why dug soil takes more space
Soil in the ground is compacted. Once dug, it loosens and takes up more room, which is called bulking or swell. Topsoil typically grows by about 25%, clay by about 30%, sand by about 12%, broken concrete by about 60% and mixed rubble by about 50%. The calculator applies this for the material you choose.
What mistakes should I avoid?
- Using the in-ground volume, forgetting bulking.
- Booking a large skip for soil, which may be refused or overweight.
- Mixing waste types that the company charges differently for.
- No permit when the skip goes on the road (councils often require one).
How is it calculated?
Dug volume = area × depth × bulking factor. Weight = in-ground volume × density. Bins needed = dug volume ÷ bin size.
Worked examples
Topsoil: Book 1 × 4 m³ skip bin for about 4.5 tonnes of topsoil. Check the hire company’s rules for heavy waste.
Breaking out a concrete patio: Book 3 × 4 m³ skip bins for about 18.4 tonnes of concrete or paving. Check the hire company’s rules for heavy waste.
What figures do we use?
- Bulking: topsoil about 25%, clay about 30%, sandy soil about 12%, broken concrete about 60%, mixed rubble about 50%
- In-ground densities from about 1.45 t/m³ (topsoil) to 2.3 t/m³ (concrete)
These are typical figures; your materials and supplier may differ.
Common questions
What size skip bin do I need for soil?
It depends on volume and the company’s heavy-waste rules; enter your dig size to see the volume once dug.
How much does soil expand when dug?
Typically 12–30%, depending on soil type. Broken concrete can bulk by about 60%, and mixed rubble by about 50%.
How heavy is a cubic metre of soil?
Roughly 1.5–1.8 tonnes, more when wet.
Can I mix soil and household waste?
Often yes, but some companies charge less for clean soil or rubble kept separate. Ask before booking.
Do I need a permit?
Often, if the bin sits on the street; check your council.