How much fall do I need for drainage?

Around a house, the National Construction Code requires the ground to fall at least 50 mm over the first metre (1:20), or 25 mm (1:40) for impermeable surfaces such as concrete or clay paving in low-rainfall areas. Subsoil drains need at least 1:300.

On this page
Gravel and perforated drainage pipe

Key facts

  • NCC: finished ground must fall at least 50 mm over the first 1 m from a house.
  • 25 mm over 1 m is allowed for impermeable surfaces in low-rainfall areas.
  • Subsoil drains need a uniform fall of at least 1:300.
  • Local plumbing and council rules may add requirements; check with your builder or plumber.

Which fall should I use?

SituationMinimum fallSource
Ground next to a house (most cases)50 mm over 1 m (1:20)NCC Housing Provisions 3.3.3
Impermeable paving, low-rainfall areas25 mm over 1 m (1:40)NCC Housing Provisions 3.3.3
Subsoil drains1:300NCC Housing Provisions 3.3.4

How do I set out a fall?

  1. Fix a string line or straight edge at the high end (next to the house).
  2. Measure the length the water will travel.
  3. Work out the total fall with the calculator, then set the low end that much lower.
  4. Check along the way with a level and a spacer, or a laser level.

What mistakes should I avoid?

  • Falling towards the house instead of away from it.
  • No fall at all: water ponds and can seep under doors.
  • Too steep on a patio, making furniture rock and paths slippery.
  • Forgetting where the water goes: fall towards a drain, gravel or lawn.

How is it calculated?

Total fall = length ÷ the ratio. A 1:60 fall over 4 m is 4,000 mm ÷ 60 ≈ 67 mm. Percentage slope = 100 ÷ ratio; the angle is the inverse tangent of 1 ÷ ratio.

Worked examples

JobTotal fall
1 m from the house at 1:2050 mm
20 m subsoil drain at 1:30067 mm

Sources

  • ABCB, NCC 2022 Housing Provisions Part 3.3: surface water drainage (3.3.3) and subsoil drainage (3.3.4)

Building codes and local rules can change, so check current requirements for your area.

Common questions

How much fall away from a house in Australia?

At least 50 mm over the first metre, or 25 mm for impermeable paving in low-rainfall areas, under the NCC.

What fall does a subsoil drain need?

At least 1:300: 3.3 mm per metre.

What is 1:100 in mm?

10 mm per metre, or 1%.

Do I need a plumber for drainage?

Stormwater connections usually need a licensed plumber; check your state’s rules.