How much fall do I need for drainage?
Around a house, the National Construction Code requires the ground to fall at least 50 mm over the first metre (1:20), or 25 mm (1:40) for impermeable surfaces such as concrete or clay paving in low-rainfall areas. Subsoil drains need at least 1:300.
On this page

Key facts
- NCC: finished ground must fall at least 50 mm over the first 1 m from a house.
- 25 mm over 1 m is allowed for impermeable surfaces in low-rainfall areas.
- Subsoil drains need a uniform fall of at least 1:300.
- Local plumbing and council rules may add requirements; check with your builder or plumber.
Which fall should I use?
| Situation | Minimum fall | Source |
|---|---|---|
| Ground next to a house (most cases) | 50 mm over 1 m (1:20) | NCC Housing Provisions 3.3.3 |
| Impermeable paving, low-rainfall areas | 25 mm over 1 m (1:40) | NCC Housing Provisions 3.3.3 |
| Subsoil drains | 1:300 | NCC Housing Provisions 3.3.4 |
How do I set out a fall?
- Fix a string line or straight edge at the high end (next to the house).
- Measure the length the water will travel.
- Work out the total fall with the calculator, then set the low end that much lower.
- Check along the way with a level and a spacer, or a laser level.
What mistakes should I avoid?
- Falling towards the house instead of away from it.
- No fall at all: water ponds and can seep under doors.
- Too steep on a patio, making furniture rock and paths slippery.
- Forgetting where the water goes: fall towards a drain, gravel or lawn.
How is it calculated?
Total fall = length ÷ the ratio. A 1:60 fall over 4 m is 4,000 mm ÷ 60 ≈ 67 mm. Percentage slope = 100 ÷ ratio; the angle is the inverse tangent of 1 ÷ ratio.
Worked examples
| Job | Total fall |
|---|---|
| 1 m from the house at 1:20 | 50 mm |
| 20 m subsoil drain at 1:300 | 67 mm |
Sources
- ABCB, NCC 2022 Housing Provisions Part 3.3: surface water drainage (3.3.3) and subsoil drainage (3.3.4)
Building codes and local rules can change, so check current requirements for your area.
Common questions
How much fall away from a house in Australia?
At least 50 mm over the first metre, or 25 mm for impermeable paving in low-rainfall areas, under the NCC.
What fall does a subsoil drain need?
At least 1:300: 3.3 mm per metre.
What is 1:100 in mm?
10 mm per metre, or 1%.
Do I need a plumber for drainage?
Stormwater connections usually need a licensed plumber; check your state’s rules.